SunPeople were engaged to design, supply and install a 99kW PV system onto a high rise commercial rooftop in Wollongong CBD. The scope of the project was to install enough PV capacity to offset airconditioning costs.
Project Details
PV System
99kW
Panels
Trina 365W x 273
Inverter
SolarEdge 27kW x 3
Mounting
Schletter Klip-Lok
Challenges
Limited roof space posed a significant challenge to install the capacity required. A package of high-powered panels and an optimised inverter system was required to attain the 99kW of PV. The prominent location and high traffic areas also presented design complications.
Outcomes
With careful management, SunPeople successfully completed the installation within the 6 week time frame, with minimal disruption to the building tenants’ strict requirements. The 99kW PV system is outperforming production estimates.